How Long Does It Take to Build an ADU?

Timeline data page Timelines as of Sep 2026 Verified Last verified 2026-09-24
Quick answer

How long does it take to build an ADU? Split it into two clocks on different tracks. The approval clock is the one states write down, and most do not: among the ten states profiled on this site, only California sets a statutory ADU decision clock (60 days from a complete application, deemed approved if missed) and Oregon sets a 120-day final-action deadline. The build clock has no national statistic; factory schedules and site works run on different tracks, and the site side stays a quote.

How long does it take to build an ADU splits into two clocks on different tracks: the approval clock, which American states rarely publish, and the build clock, which nobody publishes at all. Australia writes a determination deadline into every state's statute; the United States runs the other way. Among the ten states profiled on this site, only California and Oregon set a statutory clock that touches ADU permits. The rest delegate timing to city procedures, and this page keeps that difference on the record instead of averaging it away.

Where state law sets a clock

State Statutory clock What happens at the deadline Source
California 15 business days to send a completeness notice; then 60 days to approve or deny from a complete application Miss the completeness window and the application is treated as complete. Miss the 60-day window and the application is deemed approved, unless the applicant requested the delay Gov. Code §66317
California coast 60 days to approve or deny an ADU coastal development permit; hearings no longer required; decisions non-appealable Where no certified local coastal program exists, the Coastal Commission runs the same 60-day clock, and a missed deadline there means deemed approval, except when the ADU is filed with a new primary dwelling Gov. Code §66329, AB 462 (2025)
Oregon 120 days for a city to take final action on a land-use application; counties mirror it at ORS 215.427 The clock runs from a deemed-complete application, and extensions, on the applicant's request, can stretch it to 245 days. Building permits stay on a separate, city-published track ORS 227.178

Three readings of that table matter. California's 60-day clock is the only one among the profiled states that ends in a deemed approval: a city that does not act on a complete application in time has approved the unit. The §66317 clock also carries a patience branch: an ADU filed together with a new primary dwelling may see its decision wait for the primary's, still on the ministerial track with no hearing. Oregon's 120 days is a duty to act, not an automatic grant, so the consequence of missing it plays out in review proceedings rather than in a permit appearing. And the coastal deemed approval carries its own exception, because an ADU filed together with a new primary dwelling can wait for the primary's decision.

The states that publish no clock

State What the profile verified Source
Texas, Florida, Georgia, Arizona, Colorado, Washington No state determination deadline for ADU permits; review periods follow each city's published procedures State profiles, verified Sep 2026
Utah No deadline; a 2025 bill to add 14, 7 and 10-day clocks did not pass Utah profile
North Carolina No deadline today; S.L. 2026-59 takes applications from January 15, 2027 North Carolina profile

City procedures still write numbers of their own; they are just not state law. Austin's page publishes no fixed review period, but permits expire on the 181st day without a passing inspection, and each scheduled or passed inspection extends them by 180 days. That is an expiry clock rather than a decision clock, and the difference decides whether you chase the review or keep the permit alive.

What the clock does not cover

Every statutory period starts at a complete application, and completeness is where most calendars are lost. Drawings, the site survey, the soil report and service locates all run before the clock starts, and a resubmission after corrections restarts the review. The sequence, and the deficiencies that let a city bounce an application instead of denying it, are laid out in our permit process guide. After approval, the second layer of the stack takes over: a building permit with its own plan check, which no ADU statute merges into the 60-day or 120-day clock.

Build time: what can and cannot be published

No official national statistic exists for ADU construction duration, and this page does not invent one. What is published is structural. Factory-built units shorten schedules because manufacture runs alongside approvals, site works and freight instead of after them, and SunModu's published factory schedule is 15-20 days for standard models and 20-25 days for the 30ft series. What moves the rest of the build clock on any given site is the foundation system the soil supports, trade availability, inspection scheduling and the weather window, and those four lines belong to quotes, which is where the California cost table picks the story up. The state-by-state version of the approval clock for granny flats is in the Australian timeline.

FAQ

Two statutory windows, both in Gov. Code §66317. The city has 15 business days to send a completeness notice, and if it misses that window the application is treated as complete. From a complete application, the city has 60 days to approve or deny; no action in 60 days and the application is deemed approved, unless the applicant requested the delay. Coastal development permits run on their own 60-day clock under AB 462, and a separate building permit follows approval.

Among the ten states profiled on this site, two. California pairs a 60-day ministerial deadline with deemed approval, and Oregon requires cities to take final action on a land-use application within 120 days. Texas, Florida, Georgia, Arizona, Colorado and Washington set no determination deadline and defer to city procedures. Utah has no deadline either; a 2025 bill to add 14, 7 and 10-day clocks did not pass. North Carolina's state ADU law starts receiving applications on January 15, 2027, and sets no determination deadline of its own.

The statutory clock starts at a complete application, and completeness is where most calendars slip. Missing items must be listed and resubmitted, and the review clock restarts on the corrected set. The building permit is a second review with its own plan check, and site-specific factors such as soils, utilities or historic review sit outside the ADU statute entirely.

SunModu's published factory schedule is 15-20 days for standard models and 20-25 days for the 30ft series, and manufacture runs alongside approvals and site works rather than after them. That parallel schedule is structural, not a market average. Foundation, trenching, utility tie-ins and inspections are quoted per site, because they are facts of your lot, not factory clocks.

Factory direct

Factory schedule overlaps your permit clock

Layout, quantity and destination port in, factory price with a freight and loading plan out in one business day.

Get a factory quote
Sources & verification
  • Gov. Code §66317 (completeness notice, 60-day ministerial decision, deemed approved unless applicant delay); leginfo.legislature.ca.gov (accessed 2026-09-24)
  • Gov. Code §66329 (coastal development permit 60-day clock, hearings removed, non-appealable; added by AB 462, Ch. 491 of 2025); leginfo.legislature.ca.gov (accessed 2026-09-24)
  • ORS 227.178 and ORS 215.427 (120-day final action for land-use applications, cities and counties; extension to 245 days); oregon.public.law (accessed 2026-09-24)
  • Timeline data for the ten state profiles, including the Texas (Austin permit expiry) and Utah (failed 2025 clock bill) lines; this site, each verified Sep 2026
  • SunModu published factory lead times, 15-20 days standard and 20-25 days for the 30ft series; sunmodu.com (accessed 2026-09-24)
Verified 2026-09-24 by SunModu Atlas