Getting an ADU permit runs on the same four moves everywhere: file, pass the completeness check, receive the decision, and build to inspection. What has changed is that states now write the clock down. California gives the city 15 business days to check completeness and 60 days to decide, and a missed deadline means the application is deemed approved. Australia runs statutory clocks too, from 10 days for a NSW complying development to 42 days in Tasmania, and the clocks are tabulated here from verified sources.
Every ADU permit moves through the same four stages: the application goes in, the agency checks it for completeness, the agency decides, and the built unit is inspected to a certificate of occupancy. What separates a predictable project from a frustrating one is no longer mystery, because the better part of this database now writes the clock into statute. This page walks the four steps with California as the fullest written example, tabulates the statutory clocks we have verified, and marks the honest gaps where no state clock exists.
The four steps, in outline
| Step | What happens | Who sets the pace |
|---|---|---|
| 1. File | Drawings, forms and fees go to the city or certifier | You |
| 2. Completeness check | The agency either accepts the application or lists what is missing | State clock, where one exists |
| 3. Decision | Approve or deny, ministerially for qualifying units | State clock, where one exists |
| 4. Build and inspect | Construction under the permit, inspections called, occupancy certificate issued | Your crew and the inspector |
Steps 2 and 3 are where the statutes have taken over, and California writes both in the most detail.
Step one: the completeness check
California owes the applicant a written completeness determination within 15 business days of submission (§66317). If the application is incomplete, the notice must list the missing items and say how to cure them, and that list is the boundary: on review of the resubmission the agency cannot demand items it failed to list. An agency that misses the completeness window does not get to revive it, because the application is deemed complete. The junior ADU procedure mirrors all of it at §66335, including the rule that only a JADU ordinance consistent with the article can serve as the basis for delay or denial.
The practical reading: the completeness check is where applications actually go to age, and the statute answers it with a bounded list and a deadline. An application that survives step one intact is a different object from one that does not.
Step two: the decision clock
For a qualifying ADU with an existing single-family or multifamily dwelling on the lot, California's decision window is 60 days from the completed application, decided ministerially, which means no discretionary review and no hearing. Three adjacent clocks run on the same pattern. A two-unit project or urban lot split under SB 9 carries the same 60-day deadline with deemed approval, added by SB 450 (§65852.21, §66411.7). A coastal development permit for an ADU now runs a 60-day clock too, with no hearing required and no appeal of the decision (§66329). And an application filed together with a permit for a new home can be held until the home's decision issues, still ministerial, which is the ordinary route on a bare lot.
The word ministerial carries its own guarantee, and it is written into the definitions. Standards applied to a qualifying ADU must be objective, which the statute defines as standards involving no personal or subjective judgment by a public official, uniformly verifiable against an external benchmark knowable to both the applicant and the official before submittal (§66313(i)). The decision is supposed to be checkable the way an arithmetic problem is, which is what makes the clock enforceable at all.
Two qualifiers keep the clock honest. An applicant who requests a delay stops the 60 days for the delay's duration. And the deadline belongs to the agency from the date the application is complete, so the real elapsed time is the clock plus however long step one took.
What happens when the deadline slips
In California, nothing good for the agency: the application is deemed approved. That is the mechanism on the ADU clock, on both SB 9 paths, and on the Coastal Commission's coastal permit clock, where the exception is an application filed together with a new primary dwelling. Denial, when it comes on time, must arrive in writing with a full set of comments listing the defective items and how to remedy them. The ADU chapter bars denial over nonconforming zoning conditions, building code violations or unpermitted structures that pose no health-and-safety threat and are unaffected by the unit (§66322(b)); the written finding of a specific, adverse impact on public health and safety is the SB 9 denial gate, not the ADU clock.
Direction matters here, because not every deemed outcome favors the applicant. Tasmania's 42-day statutory window ends in a deemed grant, the same direction as California. Western Australia's 60-day statutory review window ends in the opposite: a deemed refusal. The word "deemed" tells you a deadline has consequences; the statute, not the word, tells you which side they land on.
The clocks we have verified, by jurisdiction
| Jurisdiction | Pathway | Statutory clock | Miss it and… |
|---|---|---|---|
| California, ADU | Ministerial | 15 business days + 60 days | Deemed complete / deemed approved |
| California, JADU | Ministerial | Same mirror | Deemed complete only; no deemed-approved rule (§66335(a)(3)) |
| California, SB 9 | Ministerial | 60 days | Deemed approved |
| California, coastal ADU | CDP | 60 days | Local path: no deemed consequence; Commission path: deemed approved |
| NSW, complying development | Certifier or council | 10 days, or 20 on the notification track | — |
| Queensland | Code assessment | 35 business days | Deemed approval on the applicant's notice (s 64) |
| Tasmania | Planning application | 42 days | Deemed grant |
| WA (Australia) | Development application | 60 days | Deemed refusal |
| Oregon | Statewide mandate; local permit process | 120 days to final action (ORS 227.178), extendable | — |
| Texas, Georgia and the rest | Administrative or city-set | No ADU-specific statewide clock in our profiles; Texas and Georgia decide by city | — |
Clocks above come from the statutes cited in the previous sections and from our state and timeline profiles, each carrying its own citation and verification date. The full Australian table, including South Australia's track-based periods, the ACT's four tracks and the Northern Territory's unofficial eight weeks, sits on our granny flat timeline page. Where the table says no statewide clock exists, that is our honest verification gap, not a promise about your city's counter speed; Texas and Georgia especially are city documents all the way down.
If the answer is no: appeals and second looks
The process does not end at a defective decision. A junior ADU applicant can appeal an incompleteness or denial determination in writing to the governing body, or, absent one, the agency director, or at the city's option the planning commission, or both, and the agency owes a final written determination within 60 business days of the appeal; running the appeal past two bodies does not extend that window (§66335(e)). The same right exists for ADU applications: §66317(d) provides the written appeal to the governing body or, where there is none, to the agency director, on the same 60-business-day clock. Two practical notes travel with the right: the defect list from step one bounds what the agency can demand on resubmission, and an appeal challenges the decision as made, which is why the written defect list matters at every stage before it.
What the process costs
The permit process carries fees at filing, and they are published more often than people expect. Our permit fees page quotes city fee schedules line by line, from San Diego's flat plan-check table to San Jose's dedicated ADU schedule, and the California cost table walks a full 750 sq ft example to the dollar. For a pre-submittal estimate, Los Angeles publishes an official plan check fee estimate system that estimates your project against the current fee ordinance, with final fees set when the application is submitted. State law caps the worst lines: impact fees are $0 at 750 sq ft or less, and school fees stop under 500 sq ft.
The short version
How to get an ADU permit is a four-step process, and the middle two steps now run on published clocks in the states that matter most. File a complete application, hold the agency to its completeness list, expect a ministerial decision inside the statutory window, and know that in California a missed window ends in approval rather than silence. The state profiles behind this page carry each jurisdiction's full pathway, and the fee pages carry what the counter will charge you at step one.
FAQ
Where the state writes a clock, the decision window is measured in weeks, not months. California owes you a completeness answer in 15 business days and an approval or denial in 60 days after that; a compliant application the city ignores for 60 days is deemed approved. Australia runs shorter statutory clocks on its fast tracks: 10 days for a NSW complying development, 42 days to a deemed grant in Tasmania. Your total time is the decision clock plus how long you take to reach a complete application.
Four moves. Submit drawings and the application forms your city lists. Wait out the completeness window: in California the city has 15 business days to say what is missing, and the list it gives is the list you cure, no more. Receive the decision inside the statutory window, ministerially with no hearing for qualifying units. Then build under the permit and call inspections until the certificate of occupancy issues.
Only on paper and only for cause. California requires the denial in writing with a full list of defective items and how to fix them, bars denials over nonconforming zoning conditions that pose no health and safety risk, and the written finding of a specific, adverse impact on public health and safety belongs to the SB 9 paths, not the ADU chapter. Miss the deadline instead and the application is deemed approved, not denied.
Use the estimators governments actually publish. Los Angeles runs an official plan check fee estimate system that estimates your project against the current fee ordinance before you submit, and the estimate disclaims itself: final fees are set at submittal. The fee lines themselves, from plan check to school charges, are tabulated with sources on our permit fees and California cost pages; the construction side is quoted, not estimated.
It runs on a mirror of the ADU process: ministerial consideration, the same 15-business-day completeness check and 60-day decision window, the same tolling and defect-list rules (Gov. Code §66335). One ADU plus one JADU can sit on the same lot, and a JADU ordinance consistent with the article is the only local rule that can delay or deny one.
Permit sorted? Get the unit priced.
Layout, quantity and destination port in, factory price with a freight and loading plan out in one business day, confirmed per order.
- Gov. Code §66317 (ADU completeness and decision clocks) and §66335 (junior ADU procedure, appeals); leginfo.legislature.ca.gov (accessed 2026-09-22)
- Gov. Code §65852.21 and §66411.7 (SB 9 clocks with deemed approval, SB 450) and §66329 (coastal development permit clock, AB 462); leginfo.legislature.ca.gov (accessed 2026-09-21)
- State approval clocks for Australia: EP&A Regulation 2021 cl 133-134 (NSW), Planning Act framework (QLD 35 business days), LUPAA s57 (TAS 42-day deemed grant), WA 60-day deemed refusal, SA reg 53, ACT tracks; tracked on our Australia timeline page (accessed 2026-09-22)
- LADBS Plan Check Fee Estimate System; 08web15.lacity.org/fee_est_dir (accessed 2026-09-21)
Something look off: a fee, a date, a rule? Email tianxin@sunmodu.com. Every message gets reviewed and accepted fixes are dated right here on the page, and with your okay, we'll thank you by name for pointing it out.