California allows ADUs statewide on residential lots, and cities must approve a compliant application ministerially: approve or deny within 60 days, no hearings, and the application is deemed approved if the deadline is missed (Gov. Code §66317). ADUs of 750 sq ft or less pay no impact fee (§66311.5).
What you can build
- Detached ADUs, attached ADUs, and conversions of existing space are allowed statewide on residential lots. Local ordinances cannot ban them.
- A protected baseline of an 800 sq ft unit with 4-foot side and rear setbacks cannot be reduced by local rules (§66321).
- Detached ADUs get a 16-foot height baseline (§66321). Junior ADUs (JADUs, up to 500 sq ft inside the walls of the primary home) follow their own article (§66333 et seq.). The full rules sit on our Junior ADU profile.
- No parking may be required within a half-mile walking distance of public transit, in historic districts, or where the ADU is part of the primary residence (§66322).
Approval pathway
Ministerial approval
Qualifying ADU applications are approved ministerially: without discretionary review or a hearing (§66323, §66317(a)(1)). Permits cannot be denied because of nonconforming zoning conditions or unpermitted existing structures that neither threaten public health and safety nor are affected by the ADU construction (§66322).
Local ADU ordinance
Cities apply their adopted ADU ordinance, but state law supersedes any conflicting ordinance; local agencies may only adopt less restrictive requirements (§66325). Noncompliant ordinances are null and void after HCD review (§66326).
Timeline
| Step | Statutory clock | Detail |
|---|---|---|
| Completeness review | 15 business days | Written notice of completeness; if incomplete, the notice must list missing items. Miss the deadline and the application is treated as complete (§66317). |
| Approve or deny | 60 days | From a complete application. No action in 60 days = the application is deemed approved, unless the applicant requested a delay (§66317). |
| ADU filed with a new home | With the primary | The ADU decision may wait for the new primary dwelling's decision: still ministerial, no hearing (§66317). |
Statutory clocks per state law; city practice varies and is noted per city below.
Fee rules
| Rule | Detail | Cite |
|---|---|---|
| No impact fee ≤750 sq ft | No impact fee on an ADU with 750 sq ft or less of interior livable space, or a JADU of 500 sq ft or less. | GOV §66311.5(c)(1) |
| Impact fees above 750 sq ft | Charged proportionately in relation to the square footage of the primary dwelling. | GOV §66311.5(c)(2) |
| No separate utility connection for most ADUs | Connection fees or capacity charges generally prohibited. An ADU is not a new residential use for those charges unless built with a new single-family home; qualifying units cannot be required to add a new or separate connection. | GOV §66311.5(b),(d) |
| Connection fees for other ADUs | Where allowed, charges must be proportionate to the ADU's burden (by square footage or fixture units) and not exceed the reasonable cost of service. | GOV §66311.5(e) |
| School fee exemption <500 sq ft | For school developer fees under Education Code §17620, an ADU/JADU with less than 500 sq ft of interior livable space is deemed not to increase assessable space: new as of Jan 1, 2026 (SB 543). Note the boundary differs from the impact-fee rule above: impact fees use "750 or less", school fees use "under 500". | GOV §66311.5(c)(3) |
State fee floors and caps. Actual permit fees are set per city from published fee schedules, city tables added as they are verified.
Key laws behind these rules
- GOV §66317: 15-business-day completeness check, 60-day approve-or-deny clock, deemed approved on delay text ↗
- GOV §66321: Size, setback and height floors (800 sq ft / 4 ft setbacks / 16 ft detached) text ↗
- GOV §66322: Parking relief and no denial over nonconforming conditions text ↗
- GOV §66323: Ministerial approval for qualifying ADUs text ↗
- GOV §66311.5: Impact fee and connection fee rules (renumbered from §66324 by SB 543, effective Jan 1, 2026) text ↗
- AB 976 (2023): Owner-occupancy requirements permanently prohibited for ADUs (since Jan 1, 2024); JADUs excepted text ↗
City examples
City permit practice differs sharply: San Diego publishes its full plan check and inspection table (Information Bulletin 501), Los Angeles computes building fees from project valuation while the LAUSD program office levies the state school developer fee, and San Jose prices ADUs on a dedicated flat schedule. The verified numbers per city are tabulated in the California cost table.
FAQ
State law gives the city 15 business days to check completeness and 60 days to approve or deny a complete application. If the city misses the 60-day deadline, the application is deemed approved (Gov. Code §66317). Real-world timelines depend on how quickly you reach a complete application.
No. Since January 1, 2024 (AB 976), cities cannot require the owner to occupy the ADU or the primary dwelling. For junior ADUs the rule was tightened from January 1, 2026 (AB 1154): an owner-occupancy condition can only apply where the JADU shares sanitation facilities with the primary home.
No impact fee at all (Gov. Code §66311.5), and generally no separate utility connection fee or capacity charge. School developer fees are also exempted for units under 500 sq ft as of January 1, 2026 (SB 543). Building permit and plan-check fees still apply and vary by city.
Export-grade expandable container ADUs
10ft to 40ft expandable units engineered for ADU programs: flat-packed, 15-20 day standard lead time, priced confirmed per order.
- Gov. Code §66317, §66321, §66322, §66323, §66325, §66326; leginfo.legislature.ca.gov (accessed 2026-09-21)
- Gov. Code §66311.5 (fees; renumbered from §66324 by SB 543, effective Jan 1, 2026); leginfo.legislature.ca.gov (accessed 2026-09-21)
- Gov. Code §66315 (owner-occupancy prohibition) and §66333 (JADU owner-occupancy limits, AB 1154); leginfo.legislature.ca.gov (accessed 2026-09-21)
- SB 543 (2025); AALRR client alert on school developer fees for ADUs (accessed 2026-09-21)
- AB 976 (2023, Ch. 751); owner-occupancy prohibition; leginfo bill page; HCD ADU Handbook (2026)
Something look off: a fee, a date, a rule? Email tianxin@sunmodu.com. Every message gets reviewed and accepted fixes are dated right here on the page, and with your okay, we'll thank you by name for pointing it out.