No national number exists for ADU permit cost, because no two cities compute it the same way. A permit bill has four lines: plan check, permit and inspection, impact and development fees, and school or utility charges. Cities publish those lines by flat table, project valuation or per-square-foot schedule, and the published rows below come straight from those schedules.

Search "permit cost" and you get national brackets that no counter ever charged. The honest version is smaller and more useful: an ADU permit cost is a short stack of published lines, each set by a different office, and most of those offices print their numbers. This page walks the stack, shows the three ways cities compute it, and quotes the rows we have verified. City tables grow here as schedules are verified, one line item at a time.

What a permit bill actually contains

Line What it pays for Who sets it
Plan check A reviewer's hours against your drawings, before anything is approved City building department
Permit and inspection Issuance of the permit and the field inspections during construction City building department
Impact and development fees Parks, fire, libraries, roads: the cost of new demand on public assets City council, under state fee law
School and utility charges District developer fees; water, sewer and power connections School district; utility, under state fee law

The payer changes by line, and so does the legal limit on each. California writes caps for all four into statute; most states leave every line to the city.

The three ways cities compute it

Method How it works Published example
Flat table A fixed base per project type, plus a rate per sq ft past a threshold San Diego: $8,085.26 plan check for a new detached ADU over 500 sq ft (IB 501). San Jose: flat $3,323 for an ADU up to 750 sq ft, all city lines combined
Valuation The fee rises with the project's declared construction value Los Angeles (LADBS fee ordinance); San Diego's strong-motion line also runs this way at $0.13 per $1,000
Per-square-foot rate A rate multiplied by buildable or assessable area California school developer fee, up to $5.38 per sq ft residential statewide

Knowing which algorithm a city runs tells you what moves your bill. Under a flat table, size barely matters until you cross a threshold. Under valuation, the finish level on your drawings changes the fee. Under a per-square-foot rate, every foot is priced.

State rules that change the bill

California is the only state in our coverage that writes fee caps into statute, and it caps all four lines: impact fees are $0 for an ADU of 750 sq ft or less, school fees stop for units under 500 sq ft as of January 1, 2026 (SB 543), and the utility line is tiered: ADUs within existing space pay no connection fee or capacity charge, while a new detached ADU can be required to connect, with charges proportionate to its burden (Gov. Code 66311.5). The full exemption table and a worked San Diego example live on the California cost table.

Colorado attacks the bill from the other side: HB24-1152 funds a $5M fee-reduction grant program, worth up to $15,000 per ADU, for low- and moderate-income residents in supportive jurisdictions, alongside $8M in CHFA lending.

Everywhere else in our coverage, from Texas to Washington, there is no statewide fee schedule: the city sets it, which is exactly why the state rule profiles carry city tables that load only as each row is verified against a published source.

City tables loaded so far

San Diego

Full plan check, inspection and administrative rows are on the California cost table. The lines that define the shape of the bill:

Line Published amount As of
Plan check, detached ADU over 500 sq ft (covers to 3,000 sq ft) $8,085.26 August 2026
Building inspection, same projects $8,401.90 August 2026
Plan check + inspection, detached ADU up to 500 sq ft $3,512.92 + $2,228.29 August 2026
General Plan Maintenance fee, once per project $737.00 August 2026
Collection fee, once per project $17.11 August 2026

Source: City of San Diego IB 501, downloaded from sandiego.gov on 2026-09-21.

San Jose

San Jose publishes a dedicated ADU schedule with all three city lines priced flat:

Line ADU up to 750 sq ft ADU 751 to 1,200 sq ft As of
Permit issuance $454 $681 FY 2025-26 schedule
Plan review $1,137 $1,950 FY 2025-26 schedule
Inspection $1,732 $2,520 FY 2025-26 schedule
City total $3,323 $5,151 FY 2025-26 schedule

The same schedule cuts plan review by 10 percent for modular homes, and the city's ADU FAQ states that school and parkland impact fees do not apply to ADUs under 750 sq ft. The city's fee pages currently display more than one effective date for the schedule, so the rows follow the FY 2025-26 schedule marked effective August 11, 2025.

Los Angeles

Los Angeles computes building fees from project valuation under the LADBS fee ordinance, with an official Plan Check Fee Estimate System for pre-submittal estimates (the city's disclaimer: results are estimates until the application is filed). The published line every Los Angeles ADU carries is the school developer fee, levied by LAUSD at the State Allocation Board rate, $5.38 per sq ft of new assessable space effective August 11, 2026.

FAQ

There is no single honest number. What exists is the bill's structure: in San Diego, a detached 750 sq ft ADU carries $17,278.93 in published city plan check, permit and administrative fees before the school district's charge, while California law drops the impact fee line to $0 at 750 sq ft. A city that computes from project valuation produces a different bill for the same building. The tables on this page and the California cost table quote only published numbers.

Four lines: plan check (a reviewer's hours against your drawings), permit issuance and inspections, impact or development fees (parks, fire, libraries, roads), and school or utility charges. Each line has its own payer and its own rulebook, which is why one blended average misleads.

No honest ranking exists, because cities read from different algorithms: San Diego charges a flat table, San Jose prices ADUs on a dedicated flat schedule, and Los Angeles computes from project valuation. The published bills still differ sharply: a 750 sq ft ADU pays $3,323 in San Jose city lines versus $17,278.93 in San Diego. This page quotes each city's own published rows instead of forcing a false comparison.

California does the most: impact fees are $0 for ADUs of 750 sq ft or less (Gov. Code §66311.5), school fees stop for units under 500 sq ft, and ADUs created within existing space cannot be required to add a separate connection or pay connection charges, while a new detached ADU can be required to connect with proportionate charges. Colorado runs a fee-reduction grant of up to $15,000 per ADU in supportive jurisdictions. The other states in our coverage leave fees to cities.

Factory direct

Ex-works pricing, confirmed per order

Layout, quantity and destination port in. Factory price and logistics plan out within one business day.

Get a factory quote
Sources & verification
  • Gov. Code §66311.5 (impact, connection and school fee rules); leginfo.legislature.ca.gov (accessed 2026-09-21)
  • California DGS, Office of Public School Construction: Annual Adjustment to SFP Grants and Developer Fee History ($5.38 residential, adopted 1/28/2026); dgs.ca.gov (accessed 2026-09-21)
  • City of San Diego Information Bulletin 501, Fee Schedule for Construction Permits, Structures (current revision, August 2026); sandiego.gov (accessed 2026-09-21)
  • City of San Jose, FY 2025-26 Building Division Fee Schedule (effective 8/11/2025) and ADU FAQs; sanjoseca.gov (accessed 2026-09-21)
  • LAUSD Impact Fee Rates Change notice ($5.38 residential effective 8/11/2026); impactfee.lausd.org (accessed 2026-09-21)
  • Colorado General Assembly, HB24-1152 ($5M fee-reduction grant, up to $15,000 per ADU); leg.colorado.gov (accessed 2026-09-21)
Verified 2026-09-21 by SunModu Atlas
Corrections

Something look off: a fee, a date, a rule? Email tianxin@sunmodu.com. Every message gets reviewed and accepted fixes are dated right here on the page, and with your okay, we'll thank you by name for pointing it out.